Title 12 STREETS, SIDEWALKS AND PUBLIC PLACES
Chapter 12.03 PRIVATE ROAD REQUIREMENTS
12.03.100 Performance bonds.
A surety shall be posted with the department of public works office for
Categories III through VII roads if the developer requests to delay construction
to allow the sale of property(ies) within the development before construction is
complete. This surety will guarantee the completion of the road and/or drainage
improvements that are required and shall conform to the following
conditions:
A. The surety shall be of a form approved by the Skamania County
prosecuting attorney.
B. The surety shall be equal to three hundred percent
of the total road and drainage construction estimate by the county engineer and
approved by the director of public works. Included in this estimate shall be
twenty-five percent for contingencies and inflation.
C. The surety shall be
for two years, at which time it may be extended for one additional year at the
option of the director of public works. A new amount will be calculated at that
time.
D. The surety shall be used by the director of public works to make
the required improvements if the improvements are not made in the allotted
time.
E. The surety shall include granted and notarized agreements for
access for public officials, or their designee, to ensure the completion of the
development utilizing the surety to fund the completion as designed.
F. One
hundred percent of the surety may be released upon completion of the work by the
applicant and approval of the completed work by the director of public
works.
G. No building permits for any lots within the proposed development
will be issued until the work covered by the surety has been completed and the
final approved development drawings have been recorded.
H. A surety
commensurate with the extent of work to be done shall be required and posted
with Skamania County prior to the issuance of a permit. (Ord. 2008-02 (part):
Ord. 2007-02 (part): Ord. 2000-07 (part); Ord. 1986-02 (part))