12.01.050 Approvals and inspections.

A. Approvals and inspections will be required as follows:
1. Design approval before construction work starts;
2. Inspection when the centerline and right-of-way field staking is complete;
3. Inspection when clearing and grubbing is complete;
4. Inspection when drainage structures are complete;
5. Inspection when base rock is in place;
6. Inspection when top rock is in place;
7. Inspection when paving is complete;
8. Inspection when project cleanup and signing is complete;
Important: Work can progress from one stage to the next only upon the approval from the county engineer.
B. County acceptance will take place upon specific action of the board of county commissioners by road resolution. (Ord. 1981-05 (part))